Introduction & focus areas

  • Check that the energy meter is properly connected to the RC (Rogowski Coil) before setting the energy meter.
  • The red chip / S1 of the coil must be connected to the + terminal of the energy meter.
  • The black chip / S2 of the coil must be connected to the - terminal of the energy meter.

If connected incorrectly, there is the possibility that the current will be measured incorrectly. For example, if you connect the black wire to the positive terminal of the energy meter.

You can set the meter using the following buttons:

Selects the Voltage and Current displays. In setup mode, this is the “Left” or “Back” button.

Selects the display screens for Frequency and Power Factor. In Setup mode, this is the Up button.

Selects the power supply displays. In setup mode, this is the “Down” button.

Selects the energy displays. In setup mode, this is the “Enter” or “Right” button.

2

.

Setup

To enter setup mode, press 

for 3 seconds. You will then be prompted to enter a password.

You must enter the password before you can edit the settings.

If the password is incorrect, the following appears on the screen: PASS Err

Further information regarding setup can be found in the attachment below.

3

.

Menu-option selection

1. Use  and  to

browse through the various options within the settings.

2. Press to confirm the selection.

3. If an element is blinking, it can be adjusted with and 

4. Once you have selected an option from the current layer, press  to confirm your selection. The SET indicator appears.

5. When you have set a parameter, press  to return to a higher menu level. The SET indicator disappears and you can use and to further navigate through the menu.

6. After the configuration, press repeatedly until the readings display appears.


4

.

Rogowski Coils Primary Current Input

The SDM630MCT-RC works directly with Rogowski coils without an integrator. The ratio of connected Rogowski coils should be 85mV/kA as standard.

The primary current ranges from 1A to 5000A. The unit has 3 selectable current scales:

  • For a primary current lower than 500A, CT1 (primary) should be set to 0.5kA.
  • With a primary current of 500A to 1000A, CT1 should be set to 1kA.
  • With a primary current of 1000A to 5000A, CT1 should be set to 5kA.

The CT setting of the meter must be set according to the Rogowski coil used. To find the correct CT1 setting, you can use the following table

5

.

Setup CT1

Setup CT1

Use the  and  buttons in the setup menu to select the CT option.

Press  to move to the CT primary current selection routine: 0.5kA / 1kA / 5kA.

Press   to confirm the selection. The SET indicator appears.


6

.

Eastron-SDM630MCT-RC-user-manual

Need Support?

Can’t find the answer you’re looking for? Don’t worry we’re here to help!

Ask For Help
Language Choice Disclaimer

These texts have been automatically translated using advanced AI translation tools. If you notice any inaccuracies or errors, please help us improve by sending a message to hello@calculus.group. Your feedback assists us in enhancing the quality of our multilingual documentation.