Setup Eastron SDM630-MODBUS-MID-V2-3F/100A
1
.
Instructions & focus areas
- Check that the energy meter is properly connected to the CT (current transformer) before configuring it.
- The white wire / S1 of the transformer should be connected to the + terminal of the energy meter.
- The black wire / S2 of the transformer should be connected to the - terminal of the energy meter.
- If connected improperly, there is the possibility that the current will be measured incorrectly. For example, if you connect the black wire to the positive terminal of the energy meter.
- See also the following section in the manual Eastron energy meters - installation of a CT.
Information regarding configuration can be found in the attachment below.
2
.
SDM630_series_Datasheet (1)
3
.
SDM630_Series_Manual (1)
Was this article helpful?
- Eastron energy meters manual